Construction 50% complete at Horizonte Minerals' Araguaia project
Horizonte Minerals says construction of its flagship Araguaia nickel project in Brazil remains on budget and on schedule, Kallanish reports.
The Line 1 project is expected to begin production in first quarter 2024, the company says in a construction update. It says 50% of the construction work has been completed.
Earthworks are complete and detailed engineering is 95% complete, it says. Electro-mechanical installations are advancing. Key long-lead items remain on…
This article contains premium data.
It is only available for active subscribers and clients currently
on trial. To continue reading, see the options below.
on trial. To continue reading, see the options below.
Truly global, user-friendly coverage of the steel and related markets and industry that delivers the essential information quickly while delivering on most occasions just the right amount of between-the-lines comment and interpretation for a near real time news service of this kind.
Anonymous
Very good overview of the weekly steel market.
Anonymous